Outline or full planning permission? What each costs, and how long it lasts
Full permission settles everything at once and gives you three years to start. Outline settles the principle and leaves the detail for later, on a different clock. For a landowner the choice decides what you can sell, who will want to buy it, and how long the permission stays alive.
Facts checked against the sources below on 10 November 2026.
Outline permission says yes to the principle: this many homes, on this land, with access roughly here. Full permission says yes to a specific scheme, drawn and specified down to the windows. Both are planning permission, both add value to land, and both lapse if nobody acts on them in time. They just run on different clocks, and they appeal to different buyers.
- To begin work under a full permission (the default)
- 3 years
- Outline: to apply for reserved matters, then to begin after the last approval
- 3 + 2 years
- General extension of time. You start lawfully, or you apply again
- No
How long planning permission lasts
The time limits come from sections 91 and 92 of the Town and Country Planning Act 1990. They apply to every council in England, so the rules are the same in Maidstone, Wealden or Guildford. What can differ is the decision notice itself: the council can set a shorter or longer period if it has a reason to, so always read the first condition rather than assuming three years.
| Full permission | Outline permission | |
|---|---|---|
| Day one | Permission granted. The clock starts | Outline granted. The reserved matters clock starts |
| Within 3 years | Development must be begun | An application for approval of every reserved matter must be made |
| After that | If not begun, the permission lapses | Development must be begun within 2 years of the final approval of the last reserved matter |
| Longest life without starting | 3 years | About 5 years, if reserved matters go in late in year three |
| Can the council set a different period? | Yes, longer or shorter (section 91(1)(b)) | Yes, longer or shorter, and separate periods for separate parts (section 92(4) and (5)) |
The outline clock only gives you more time if you use it. Approve the reserved matters a year after the outline and you have to start by year three, exactly as with full permission. The extra two years only come if the reserved matters go in late.
How long each permission can stay alive without work starting
Years from the first grant, on the default time limits
- Time to apply for reserved matters
- Council deciding reserved matters
- Time to begin work
Show the numbers
| Time to apply for reserved matters | Council deciding reserved matters | Time to begin work | Total | |
|---|---|---|---|---|
| Full permission | 0 | 0 | 3 | 3 |
| Outline, reserved matters approved in year one | 0.75 | 0.25 | 2 | 3 |
| Outline, reserved matters applied for at the deadline | 3 | 0.25 | 2 | 5.25 |
Default periods from sections 91 and 92 of the Town and Country Planning Act 1990. The three months for the council to decide reserved matters is our assumption; the legal period for a minor scheme is eight weeks, and many take longer. Your decision notice may set different periods.
What reserved matters are
An outline application has to describe the use and how much development you're proposing, and it has to show where the access points will be, even if access itself is reserved. Everything else can be left for later. The five reserved matters are defined in the Development Management Procedure Order 2015:
Access
How vehicles, cycles and pedestrians get to and around the site, and how that fits the roads and paths around it.
Appearance
What the buildings look like: architecture, materials, decoration, lighting, colour and texture.
Landscaping
Fences and walls, planting of trees, hedges and grass, earthworks, and gardens and open spaces.
Layout
Where the buildings, routes and open spaces sit in relation to each other and to what is around the site.
Scale
The height, width and length of each building in relation to its surroundings.
You don't have to reserve all five. On a field with a tricky junction, it's common to settle access in the outline so a buyer knows the site can be reached, and reserve the rest. The council can also tell you, within a month of receiving an outline application, that it won't decide it without more detail on particular matters.
Outline permission is only for building. It can't be used for a change of use on its own, such as converting a barn to a house, which needs a full application or, where it qualifies, a Class Q prior approval.
Outline or full: the comparison
| Outline | Full | |
|---|---|---|
| What it settles | The principle, the amount of development and the access points | The whole scheme, as drawn |
| Detail needed to apply | Use, number of homes, site plan, access points, plus the surveys the council needs (ecology, trees, drainage, highways as relevant) | Full drawings of every building and the layout, plus the same surveys |
| Council fee from 1 April 2026 | £610 per 0.1 ha under 0.5 ha, then reserved matters at the full rate | £610 per home, for up to nine homes |
| Time to get to a start on site | Two applications, so longer overall | One application |
| Value to a buyer | Certainty on the principle; design risk stays with the buyer | Certainty on what can be built; little left to win or lose |
| Who it suits | Developers, who want to design their own scheme | Self-builders and small builders, who want to start quickly |
| Main risk | Reserved matters can still be refused, and the deadline to apply for them can't be extended afterwards | A buyer may want a different design and apply again anyway |
What the fees come to
The council's fee for outline permission for housing is charged by site area, while a full application is charged per home. Approval of reserved matters is charged at the full application rate for the homes it covers. So in council fees alone, outline always ends up dearer once the reserved matters are paid for. On a large plot for one house, the outline fee on its own is higher than a full application.
Council fees: outline then reserved matters, against full
Applications for new homes in England, fees from 1 April 2026
- Outline application
- Reserved matters
- Full application
Show the numbers
| Outline application | Reserved matters | Full application | Total | |
|---|---|---|---|---|
| 1 home on 0.25 ha: outline route | £1,830 | £610 | £0 | £2,440 |
| 1 home on 0.25 ha: full | £0 | £0 | £610 | £610 |
| 4 homes on 0.4 ha: outline route | £2,440 | £2,440 | £0 | £4,880 |
| 4 homes on 0.4 ha: full | £0 | £0 | £2,440 | £2,440 |
| 9 homes on 0.9 ha: outline route | £5,931 | £5,490 | £0 | £11,421 |
| 9 homes on 0.9 ha: full | £0 | £0 | £5,490 | £5,490 |
Outline: £610 per 0.1 hectare or part under 0.5 ha, £659 per 0.1 ha or part from 0.5 to 2.5 ha. Full: £610 per home for up to nine homes. Reserved matters: the full application fee, assuming one application covering every home. Source: MHCLG fee schedule from 1 April 2026.
The council fee isn't the main cost, though. A full application needs an architect to design every building, and often more detailed drainage and highways work, before you know whether the principle will be accepted. An outline lets you test the principle first and leave the design spend to whoever builds. Our guide to what planning permission costs breaks down the professional fees as well.
Starting in time: what counts
A permission is kept alive by beginning the development before the deadline. Section 56 of the 1990 Act says development begins on the day any 'material operation' starts. That means any of:
- construction work in the course of putting up a building, or demolishing one;
- digging a trench for the foundations of a building;
- laying an underground main or pipe to the foundations, or to that trench;
- any work laying out or building a road, or part of one.
A short length of foundation trench or a stretch of the access road can be enough, and once development has lawfully begun the permission doesn't lapse. If work then stalls, the council can serve a completion notice under section 94 of the 1990 Act, giving at least 12 months and taking effect only if the Secretary of State confirms it. A replacement regime (section 93H) has been enacted but isn't yet in force. You can also apply for a lawful development certificate under section 191 (or section 192, for the work still to come) confirming that the permission was begun in time, which helps when selling.
When the clock is running out
There's no general power to extend a planning permission in England. Section 73 lets you vary conditions, but subsection (5) specifically stops it being used to extend the time to begin or to apply for reserved matters, and section 73 can't be used at all once a permission has expired without being begun. That leaves:
Start lawfully before the deadline
Discharge the pre-commencement conditions, then carry out a material operation. Record it with dated photographs.
Apply again
A fresh application, outline or full, with a new fee, assessed against the policies in force when it is decided. If policy has moved against the site since the first permission, it may be refused. If it has moved in its favour, the new permission can be a better one.
On outline: get the reserved matters in on time
Once the three years have passed, no new reserved matters application can be made. An application made in time can still be approved after the deadline, and the two-year clock to begin runs from that approval. While the window is open you can also apply again with different details for the same matter.
Which to go for when you're selling land
Selling to a developer: usually outline. A housebuilder will want to design its own scheme, to its own house types, and will submit its own reserved matters. Full permission on someone else's design is, in our experience, usually redrawn after the sale, so the spend on detailed drawings is wasted. Outline proves the principle, which is what moves the land value, and leaves the developer free to design. In our experience it's the usual route under option agreements and promotion agreements, and our guide to selling to a developer covers how the price is agreed. Watch the deadline: a developer who buys late in the three-year window has very little time for reserved matters.
Selling self-build plots: more certainty is needed. A family buying a single plot doesn't want to inherit planning risk on its own home. Bare outline permission, with the design wide open, is a harder sell. Two approaches work better:
- Outline with a design code. The outline fixes the plot boundaries, access and the scale each plot can take, with a design code or plot passport setting out the rules for appearance and materials. Each buyer then applies for reserved matters for their own house within those rules. Ask the council, at outline stage, for separate reserved matters periods for separate plots, which section 92(5) allows, so a slow plot sale doesn't put the rest at risk.
- Full permission, plot by plot. Simplest for a buyer, who can start straight away, but less flexible: a buyer who wants a different house has to apply again. It suits small numbers of plots in sensitive places, such as a conservation area, where the council wants to see the design anyway.
Our comparison of the two routes sets out what each typically pays the landowner.
Permission in principle: a third route
For smaller housing schemes, those that aren't major development (broadly, fewer than ten homes), there's a lighter option. Permission in principle settles the location, land use and amount of development, for a fee of £531 per 0.1 hectare, and lasts three years when granted on application. A second stage, technical details consent, then grants the actual planning permission. It works in a similar way to outline and reserved matters, with less information needed at the first stage. See our permission in principle guide.
Before you choose
Decide who your buyer is
A developer usually wants outline. Self-builders want certainty on what they can build.
Settle access early
If access is the weak point, include it in the outline rather than reserving it.
Read the decision notice
Note the time-limit conditions and every pre-commencement condition, with dates in your diary.
Allow for decision times
Applications often run past their legal deadlines. Our study of decision times shows how long councils in Kent, East Sussex and Surrey are taking for small housing schemes.
If you want to know what the land is worth before deciding, our land value calculator works from your postcode and the size of the site.
Read next
- Selling land to a developer: how it works and what you're paidThe four ways to sell land to a developer, how a developer works out what to pay, what they check before buying, how long it takes, and the traps to avoid.
- Option agreements: the terms that matter to landownersHow an option agreement on land works: the option fee, how the price is set, the discount, minimum price, longstop date, tax, and promotion agreements.
- A third of small housing applications in Kent, East Sussex and Surrey are now decided within eight weeksOnly 34% of applications for one to nine homes in Kent, East Sussex and Surrey were decided within eight weeks in the year to June 2026, against 77% in 2010.
Common questions
How long does planning permission last?
In England, full planning permission normally lasts three years from the date it is granted: the development must be begun within that time or the permission lapses. The council can set a different period, which will be stated in a condition on the decision notice. Once development has lawfully begun, the permission doesn't expire, although the council can serve a completion notice if work stalls, which only takes effect if the Secretary of State confirms it.
How long does outline planning permission last?
An application for approval of all the reserved matters must normally be made within three years of the outline permission being granted. Development must then begin within two years of the final approval of the last reserved matter. So if the reserved matters are applied for late in the third year, the permission can stay alive for five years or a little more. The council can set different periods.
What are reserved matters?
The five aspects of a scheme that can be left out of an outline application and approved later: access, appearance, landscaping, layout and scale. They are defined in article 2 of the Town and Country Planning (Development Management Procedure) (England) Order 2015. You can include details of any of them in the outline application, and anything you include is no longer reserved.
Can you extend planning permission in England?
Not as such. Section 73(5) of the Town and Country Planning Act 1990 stops a section 73 application being used to extend the time to begin development or to apply for reserved matters. The options are to begin the development lawfully before the deadline, or to make a fresh application. The only automatic extensions are where the permission is challenged in the courts: the clock runs on for a year when a court gives permission for the challenge to proceed, with further extensions if the case is appealed (rules rewritten on 18 February 2026).
What counts as starting work on a planning permission?
Under section 56 of the Town and Country Planning Act 1990, development is begun on the date any 'material operation' starts. That includes construction work on a building, demolition, digging a trench for foundations, laying an underground main or pipe to the foundations, and laying out a road. Work done before the pre-commencement conditions have been discharged is unlawful and may not count.
Is outline planning permission cheaper than full?
The outline fee is charged by site area, £610 for each 0.1 hectare on sites under half a hectare, while a full application for up to nine homes is £610 a home. You then pay again for reserved matters, at the full application rate. For one house on a quarter-hectare plot, outline plus reserved matters comes to £2,440 in fees against £610 for full. The saving with outline is in the design and survey work you don't need up front.
Sources
- Town and Country Planning Act 1990, section 91 (general condition limiting duration of planning permission)
- Town and Country Planning Act 1990, section 92 (outline planning permission)
- Town and Country Planning Act 1990, section 92A (extension of outline permission in event of legal challenge, inserted 18 February 2026)
- Planning and Infrastructure Act 2025, section 56 (extension of time in event of legal challenge)
- Town and Country Planning Act 1990, section 56 (time when development begun; material operation)
- Town and Country Planning Act 1990, section 73 (applications to vary conditions; subsections (4) and (5))
- Town and Country Planning Act 1990, sections 94 and 95 (completion notices; confirmation by the Secretary of State). The page shows 'in Wales' wording from a 2023 amendment not yet commenced for England
- Development Management Procedure Order 2015, article 2 (reserved matters defined)
- Development Management Procedure Order 2015, article 5 (applications for outline planning permission)
- MHCLG, Planning fees: annual indexation from 1 April 2026
- Fees Regulations 2012, Schedule 1 Part 1 (reserved matters fees)
- MHCLG, Planning Practice Guidance: Making an application (outline and reserved matters)
- MHCLG, Planning Practice Guidance: Use of planning conditions
- MHCLG, Planning Practice Guidance: Flexible options for planning permissions (section 73)
- MHCLG, Planning Practice Guidance: Permission in principle
- Levelling-up and Regeneration Act 2023, section 112 (new completion notice regime, sections 93H to 93J; in force only for making regulations)
- Town and Country Planning Act 1990, section 191 (certificate of lawfulness of existing use or development)
- Draft Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026 (proposed fees from 8 December 2026)
This guide is general information, not legal, tax or financial advice. Every site is different: take advice from a solicitor and an accountant before you sign anything.