Permission in principle: a cheaper first test for a garden plot or paddock

Permission in principle lets you ask the council one question before you pay for drawings and surveys: will you accept homes here, and how many? Here's what it settles, the fees and timings from April 2026, what happens at the second stage, and when it's the right move for a garden, a paddock or a village-edge field.

Facts checked against the sources below on 10 November 2026.

A normal planning application asks the council to judge the whole scheme at once: where the homes go, how they look, the access, the trees, the drainage. To get that far you pay for drawings and reports before you know whether the council will accept any homes at all. Permission in principle splits the question in two. First, is this a place for housing, and how much? Then, separately, is this the right scheme? For a landowner with a large garden or a small paddock, that first question is often the only one that matters.

Fee for each 0.1 hectare of site, from 1 April 2026
£531
The council's statutory time to decide
5 weeks
To get technical details consent decided
3 years
Of PiP applications granted in England, April to June 2026
51%

What permission in principle settles

Three things, and only three: the location of the site, the land use, which has to be housing-led (other uses are allowed only if housing takes up most of the floorspace), and the amount of development. The amount is given as a range, a minimum and maximum net number of homes, so a grant might say "one to two dwellings" on a garden or "four to six" on a paddock.

Everything else waits for the second stage: the design, the layout, the access details, landscaping, drainage. The council can't attach conditions to a permission in principle and can't ask for a section 106 agreement. It can, though, say on the decision notice what it expects to see later, such as a tree survey or a highways assessment.

That doesn't make it a formality. The council decides it against its local plan and national policy, like any other application, and if the principle is wrong, a range of homes won't save it. Location, in planning, takes in flood risk, heritage, the green belt and whether the site can be reached safely, so all of those can sink a PiP application.

Two routes to permission in principle

Applying yourself, or the council's brownfield register
Application to the councilBrownfield land register, Part 2
Who starts itAnyone, including the landownerThe council
Which landAny land, including gardens and fieldsPreviously developed land only
Size limitFewer than 10 homes, under 1 ha, under 1,000 m² of new floorspaceNo 'major development' bar
Fee£531 per 0.1 haNone
How long it lasts3 years by default5 years by default
If the answer is noAppeal within 6 monthsNo appeal; apply instead

For most of our readers the brownfield route doesn't apply. The national definition of previously developed land excludes residential gardens in built-up areas, and land last used by agricultural buildings, so a garden or a paddock won't go on the register. It's the application route that matters.

What can't use permission in principle

The council isn't allowed to grant it on an application for:

  1. Major development

    Ten or more homes, 1,000 m² or more of new floorspace, or a site of 1 hectare or more. Note that the 1 hectare limit is wider than the usual 0.5 hectare test, which applies to housing schemes where the number of homes isn't fixed, so a 0.8 hectare field for eight homes can still use PiP.

  2. Development that needs an Environmental Impact Assessment

    Rare for a handful of homes. Where a scheme falls into the screening category, the council has to confirm it isn't EIA development before it can grant PiP.

  3. Habitats development

    Homes likely to have a significant effect on a protected European wildlife site, unless an appropriate assessment concludes, after mitigation, that they won't harm it. Parts of Kent, East Sussex and Surrey sit close to such sites (Ashdown Forest and the Thames Basin Heaths, for example), so check whether your council asks for mitigation on new homes.

  4. Householder development

    Extensions and outbuildings for your own house. PiP is for new homes.

The fees, against outline and full applications

PiP is charged on site area. The second stage, technical details consent, is charged like a full application: £610 for each new home where there are fewer than ten. Here's how the council fees compare for two typical sites, a 0.15 hectare garden with room for two homes and a 0.4 hectare paddock for five.

Council fees to reach full planning permission, three routes

England, fees from 1 April 2026. First stage and second stage.

  • First stage
  • Second stage
Show the numbers
First stageSecond stageTotal
Garden, 0.15 ha, 2 homes: PiP + technical details£1,062£1,220£2,282
Garden: outline + reserved matters£1,220£1,220£2,440
Garden: full application£1,220£0£1,220
Paddock, 0.4 ha, 5 homes: PiP + technical details£2,124£3,050£5,174
Paddock: outline + reserved matters£2,440£3,050£5,490
Paddock: full application£3,050£0£3,050

PiP £531 and outline £610 for each 0.1 ha or part of it; full application, technical details consent and first reserved matters £610 per home. Council fees only: drawings, surveys and consultants are extra. Source: Planning Portal fee guide for England from 1 April 2026, based on the Fees Regulations 2012 as amended.

On council fees alone, PiP is not the cheap option. For the garden, PiP then technical details consent comes to £2,282, against £2,440 for outline then reserved matters and £1,220 for a full application. For the paddock it's £5,174, £5,490 and £3,050. Going straight to a full application costs least, because you pay once. The saving PiP offers is elsewhere: a full application for a new house needs scaled plans and elevations, often a tree survey, an ecology report and an access assessment, and in our experience that work usually costs several times the council fee. With PiP you spend £1,062 on the garden, or £2,124 on the paddock, to find out whether that spending is worth it.

Our guide to what planning permission costs sets out the other fees in full.

From application to planning permission: the steps

  1. Apply: form, location plan, fee

    That's all the law requires: the application form, a plan identifying the land, drawn to a stated scale with north shown, and the fee. Councils can't impose their usual list of supporting documents on a PiP application. You can volunteer more, and on a site with an obvious question, such as access, a short note answering it is worth including.

  2. Publicity: 14 days

    The council puts up a site notice and an online notice, each for at least 14 days, and consults any statutory bodies that apply, who have 14 days to reply. Neighbours can comment.

  3. Decision: 5 weeks

    Counted from the day after a valid application arrives, unless you agree a longer period in writing. In April to June 2026, 155 of the 551 PiP decisions in England came within five weeks, and 268 were made under an agreed extension. Expect the council to ask for one.

  4. If it's refused: appeal or rethink

    You can appeal to the Secretary of State within six months of the decision. The refusal notice has to give full reasons, which tells you whether the problem is the site or the number of homes.

  5. If it's granted: three years for technical details consent

    Now you pay for the detailed scheme: drawings, access, layout and the reports the site needs. The application has the same requirements as a full application and must sit within the PiP's range of homes. It has to cover the whole scheme in one go: you can't phase it.

  6. Technical details consent: 5 weeks, then you have planning permission

    For fewer than ten homes the council has five weeks (ten weeks for a major scheme), with a site notice of at least 21 days. It can attach conditions and agree a section 106. Once granted, you have planning permission. If it's refused, the PiP still stands and you can apply again while it lasts.

How often councils say yes

PiP is a small route. Across England, councils decided 551 applications in April to June 2026 and refused 272 of them, about half. In our view that partly reflects the sites PiP attracts: the speculative ones, where the owner isn't sure of the answer. Here's the same quarter in Kent, East Sussex and Surrey.

Permission in principle decisions, April to June 2026

Applications granted and refused by councils in each county

  • Granted
  • Refused
Show the numbers
GrantedRefusedTotal
Kent (13 councils incl. Medway)10717
East Sussex (5 councils)51116
Surrey (11 councils)8816

Source: MHCLG live table PiP/TDC, district planning authorities, April to June 2026, summed by county. One quarter only, so small numbers. Tandridge (9 decisions, 4 granted) and Wealden (8, 4 granted) decided the most; Rother refused all 5 of its applications.

What PiP means for BNG, CIL and section 106

Biodiversity net gain. Permission in principle isn't planning permission, so it's outside BNG. Technical details consent is planning permission, so BNG applies to it unless an exemption does. Since 6 August 2026 sites of 0.2 hectares or less are exempt, as long as no priority habitat such as a native hedgerow is affected, so the garden in our example would usually escape it and the paddock wouldn't. Our BNG guide explains the exemption and what a shortfall costs.

Community Infrastructure Levy. CIL can apply once technical details consent is granted, where your council charges it, and becomes due when work starts. A self-builder who will live in the home for three years can claim exemption, but it must be granted before any work starts, or it is lost. A commencement notice must also reach the council before work starts, or a surcharge of up to £2,500 applies.

Section 106. Not possible at the PiP stage. The council can ask for one at the technical details stage, as with any planning application.

When PiP is a good move, and when it isn't

Is permission in principle the right first step?
PiP makes senseGo another way
The questionWhether the council will accept homes here at allHow the homes look, or exactly where they sit
The siteSimple: a large garden, a gap in a village street, a small paddock with an existing accessComplicated access, a listed building next door, a flood zone, protected trees
Your planTest before spending on drawings, or sell to a self-builder or small builder with the principle settledBuild yourself soon, with a design already in mind: a full application is cheaper
TimingYou or a buyer can do the detailed work within three yearsYou'd want longer to sell or plan

The weakness of PiP is that the hard questions on a difficult site are usually about detail. Can a car get in and out safely? Will the new house overlook next door? Can the drainage work? A council can't answer those without drawings, so it may refuse the principle rather than take the risk, or grant it and leave you to find out at the second stage that the scheme you wanted doesn't fit. On a site like that, a well-prepared outline or full application is often the better bet.

Our guide to outline or full planning permission compares those two routes.

For a simple garden plot, PiP can be a sensible first step. Since August 2026 national policy gives substantial weight to new homes within existing plots in towns and villages, within a set yardstick. Our guide to building a house in your garden covers what councils look for, and what garden land is worth shows what a plot could sell for.

Before you apply

  1. Measure the site

    The fee is per 0.1 hectare or part, so 0.21 hectares costs the same as 0.3. Draw the red line to include the access to the road. Keeping it to 0.2 hectares or less can also mean no BNG at the second stage.

  2. Read the local plan for your village

    Is the site inside the settlement boundary, in the green belt, in a National Landscape? The council will decide the principle on those policies.

  3. Pick a realistic range of homes

    Ask for a range the site can clearly take. A maximum the council thinks is too high can sink the whole application.

  4. Work out what you'll do in the three years

    Build, sell, or bring in a partner. Our land value calculator gives a first figure for what the land could be worth with planning.

Common questions

What is permission in principle?

Permission in principle is the first of two stages in a route to planning permission for housing-led development in England. It establishes whether a site is suitable in principle, by settling the location, land use and amount of development. The second stage, technical details consent, assesses the detailed scheme. Only when technical details consent is granted do you have planning permission.

How much does a permission in principle application cost?

From 1 April 2026 the fee in England is £531 for each 0.1 hectare of the site, or part of 0.1 hectare. A 0.15 hectare garden costs £1,062 and a 0.4 hectare paddock £2,124. Technical details consent is then charged like a full application, at £610 for each new home where there are fewer than ten.

How long does permission in principle last?

Three years by default where it was granted on an application, and five years where it was granted by entering a site on Part 2 of a brownfield land register. The council can set a shorter or longer period if it gives reasons. Technical details consent has to be decided within that period, not just applied for.

What is technical details consent?

Technical details consent is the second stage after permission in principle. The application needs the same information as a full planning application: drawings, access, layout, design and any reports the site needs. It must match the permission in principle, it can carry conditions and a section 106 agreement, and granting it has the effect of granting planning permission. The council has five weeks to decide it for a scheme of fewer than ten homes.

Can permission in principle be refused or appealed?

Yes, it can be refused, and roughly half of applications in England were refused in April to June 2026. If it's refused on an application, you can appeal to the Secretary of State within six months of the decision. There's no appeal where a council decides not to put a site on Part 2 of its brownfield land register.

Can I sell land with permission in principle?

Yes. A buyer can apply for technical details consent; whoever applies completes an ownership certificate confirming the landowner has been notified. Buyers will take into account how much of the three years is left, because technical details consent has to be decided before the permission in principle expires.

Sources

  1. MHCLG, Planning Practice Guidance: Permission in principle
  2. The Town and Country Planning (Permission in Principle) Order 2017 (as amended), articles 5A to 5V and 7
  3. Town and Country Planning Act 1990, sections 59A(7) to (8) (duration) and 70(2ZZA) to (2ZZC) (technical details consent)
  4. The Town and Country Planning (Development Management Procedure) (England) Order 2015, article 34 (time limits for technical details consent)
  5. The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012 (as amended)
  6. Planning Portal: A guide to fees for planning applications in England, from 1 April 2026
  7. MHCLG, Live tables on planning application statistics: table PiP/TDC, April to June 2026
  8. MHCLG, Planning Practice Guidance: Brownfield land registers
  9. NPPF (August 2026) Annex B: Glossary (previously developed land excludes residential gardens in built-up areas)
  10. NPPF (August 2026) Chapter 12, policy L2: new homes within residential plots
  11. MHCLG, Planning Practice Guidance: Biodiversity net gain (updated 31 July 2026)
  12. Defra, Biodiversity net gain: exempt developments (updated 6 August 2026)
  13. MHCLG, Community Infrastructure Levy guidance (self-build exemption)
  14. Draft Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026 (proposed fees from 8 December 2026)

This guide is general information, not legal, tax or financial advice. Every site is different: take advice from a solicitor and an accountant before you sign anything.