A third of small housing applications in Kent, East Sussex and Surrey are now decided within eight weeks

The legal period for deciding an application for up to nine homes is eight weeks. In 2010, councils in Kent, East Sussex and Surrey decided 77% of them within eight weeks. In the year to June 2026 it was 34%. We looked at every council's figures.

Facts checked against the sources below on 10 November 2026.

decided within eight weeks, down from 77% in 2010
34%
decided under an agreed extension of time
59%
small housing decisions than in 2018
39% fewer

The share decided within eight weeks has fallen from 77% to 34% since 2010

Applications for one to nine homes, 29 councils in Kent, East Sussex and Surrey. Years to 30 June.

0%25%50%75%100%201020122014201620182020202220242026within eight weeks, 2010: 77.1%within eight weeks, 2011: 71.1%within eight weeks, 2012: 69.5%within eight weeks, 2013: 65.3%within eight weeks, 2014: 65.2%within eight weeks, 2015: 52.4%within eight weeks, 2016: 49.2%within eight weeks, 2017: 48.2%within eight weeks, 2018: 46%within eight weeks, 2019: 37.8%within eight weeks, 2020: 39.8%within eight weeks, 2021: 35.7%within eight weeks, 2022: 30.7%within eight weeks, 2023: 32%within eight weeks, 2024: 35.9%within eight weeks, 2025: 36.8%within eight weeks, 2026: 33.7%34%agreed extension, 2015: 18.8%agreed extension, 2016: 31.3%agreed extension, 2017: 37.6%agreed extension, 2018: 42.4%agreed extension, 2019: 49.9%agreed extension, 2020: 49.1%agreed extension, 2021: 50.4%agreed extension, 2022: 50.7%agreed extension, 2023: 55.9%agreed extension, 2024: 54.5%agreed extension, 2025: 56.5%agreed extension, 2026: 58.8%59%32%
  • Decided within eight weeks
  • Decided under an agreed extension (first full year counted: 2015)
  • England, within eight weeks (dashed)
Show the numbers
Year to JuneDecisionsWithin eight weeksAgreed extensionEngland, within eight weeks
20103,82377.1%not recorded72.7%
20113,89871.1%not recorded66.6%
20123,72069.5%not recorded62%
20133,63265.3%not recorded60.3%
20143,71165.2%not recorded60.7%
20154,28252.4%18.8%53.4%
20164,36649.2%31.3%50.9%
20174,81548.2%37.6%49.6%
20184,88146%42.4%46.9%
20194,56237.8%49.9%41.7%
20204,26639.8%49.1%39.4%
20214,01535.7%50.4%34.9%
20224,01130.7%50.7%29.1%
20233,85432%55.9%29.6%
20243,62935.9%54.5%32.2%
20253,03036.8%56.5%33.6%
20262,95533.7%58.8%32.3%

Source: MHCLG, District planning application statistics (PS2), open data to 30 June 2026, published 24 September 2026. Minor dwellings: one to nine homes on a site under one hectare.

Most decisions now run on an agreed extension

Councils and applicants can agree in writing to a later decision date. The government's figures have counted these decisions separately since April 2014, and treat those made by the agreed date as on time, which most are. Their share of small housing decisions here has grown from 19% in the year to June 2015, the first full year counted, to 59% in the year to June 2026. The figures don't record how long those applications took, so the share decided within eight weeks is the only true measure of speed.

Fewer small schemes are being decided

Small housing decisions fell 39% from the 2018 peak

Decisions on applications for one to nine homes, 29 councils, years to 30 June

'14: 3,7113,711'14'15: 4,2824,282'15'16: 4,3664,366'16'17: 4,8154,815'17'18: 4,8814,881'18'19: 4,5624,562'19'20: 4,2664,266'20'21: 4,0154,015'21'22: 4,0114,011'22'23: 3,8543,854'23'24: 3,6293,629'24'25: 3,0303,030'25'26: 2,9552,955'26

Source: MHCLG, District planning application statistics (PS2), open data to 30 June 2026, published 24 September 2026. Minor dwellings: one to nine homes on a site under one hectare.

England followed the same path, from 57,780 decisions to 32,815. The figures count decisions, not applications, so they show how many small schemes reached a decision each year.

Approval rates run from under half to almost nine in ten

Tunbridge Wells approved 88% of small housing applications. Gravesham approved 49%

Share of decisions on one to nine homes that were approvals, three years to June 2026

Show the numbers
CouncilDecisionsApprovedWithin eight weeksAgreed extension
Tunbridge Wells53787.5%58.7%38.5%
Sevenoaks65579.8%46.9%51.1%
Tonbridge and Malling29978.6%23.7%65.2%
Dover28778%20.2%70%
Eastbourne7676.3%30.3%47.4%
Guildford51475.5%11.9%78%
Medway30574.8%49.5%43.3%
Lewes22974.7%31.9%41.5%
Canterbury21974.4%18.7%60.7%
Rother40372.7%29.5%65.3%
Thanet36572.6%27.7%58.1%
Hastings17671.6%35.2%64.8%
Elmbridge67371.2%35.5%58.5%
Waverley53770.2%27.2%67.2%
Swale25469.7%17.3%76.8%
Reigate and Banstead37468.4%40.6%53.2%
Runnymede26068.1%28.1%63.1%
Wealden60968%32.8%61.6%
Tandridge37567.2%26.4%64.8%
Ashford37166.3%25.6%60.9%
Surrey Heath12464.5%28.2%63.7%
Epsom and Ewell17663.1%50.6%38.1%
Maidstone45162.5%59.2%37.9%
Woking13060.8%23.1%56.9%
Folkestone and Hythe25359.7%62.1%29.2%
Spelthorne20159.7%54.7%44.3%
Dartford15353.6%31.4%64.7%
Mole Valley41849.8%36.6%49.5%
Gravesham19048.9%49.5%44.7%

Source: MHCLG, District planning application statistics (PS2), open data to 30 June 2026, published 24 September 2026. Minor dwellings: one to nine homes on a site under one hectare.

A low approval rate says as much about what gets applied for as about the council. Much of Mole Valley, Gravesham and Dartford is Green Belt. Eastbourne made fewer than 100 decisions over the three years, so it's shown in grey: a handful of decisions moves its rate.

Speed varies just as much

Folkestone and Hythe decided 62% within eight weeks. Guildford decided 12%

Share of decisions on one to nine homes made within eight weeks, three years to June 2026

Source: MHCLG, District planning application statistics (PS2), open data to 30 June 2026, published 24 September 2026. Minor dwellings: one to nine homes on a site under one hectare.

Check a council

In the three years to June 2026, Tonbridge and Malling approved 78.6% of applications for one to nine homes, above the England figure of 72.7%, and decided 23.7% within eight weeks. In 2010 it was 76.6%.

Approved
78.6%
of 299 decisions over three years
Within eight weeks
23.7%
76.6% in 2010
Decisions a year
108
123 in 2018

If you're applying for a small scheme

  1. Plan for more than eight weeks

    Eight weeks is the legal period, but in most councils here fewer than half of small housing decisions are made within it without an agreed extension.

  2. Expect to be asked for an extension

    Councils often ask applicants to agree a later date. You don't have to agree, and it's worth asking what is still outstanding before you do.

  3. Know your fallback

    If there's no decision by the deadline or the agreed date, you can appeal to the Planning Inspectorate against non-determination.

How we did this

We used MHCLG's PS2 planning statistics for every council in Kent, Medway, East Sussex and Surrey, and took the "minor dwellings" category: applications for one to nine homes on a site under one hectare. Years run to 30 June. "Within eight weeks" counts decisions made in eight weeks or less without an extension. MHCLG's extension category also covers planning performance agreements and the rare application needing an environmental impact assessment. A decision made under an extension is counted with the extensions even if it came early, so this slightly understates the true share since 2014. Before April 2014 the figures didn't separate extensions, so decisions made under one were counted by the time they actually took. Council rankings use three years of decisions, because a single year can rest on fewer than 50 decisions in a small council.

Common questions

How long does planning permission take for one to nine homes?

The legal period for a council to decide an application for one to nine homes is eight weeks from when it receives a valid application, unless you agree a longer period in writing. In the year to June 2026, councils in Kent, East Sussex and Surrey decided about a third of these applications within eight weeks. Most of the rest were decided under an agreed extension of time.

What is an extension of time?

An extension of time is a written agreement between the council and the applicant to decide an application by a later date. A decision made by the agreed date counts as on time in the government's performance figures, however long it took. The figures don't record how long those decisions actually took.

What counts as a small housing application?

In the government's planning statistics, a 'minor dwellings' application is for one to nine homes on a site under one hectare. If the number of homes isn't known, a site under half a hectare counts as minor. Ten or more homes, or a site of a hectare or more, is a major application with a 13-week period.

What can I do if the council doesn't decide in time?

If there's no decision by the end of the eight weeks, or by a later date you've agreed, you can appeal to the Planning Inspectorate against non-determination. If you haven't appealed or agreed an extension and there's still no decision after 16 weeks, the council must refund the application fee. In practice many applicants agree an extension instead, because an appeal takes months and the council may still be working on the application.

Sources

  1. MHCLG, District planning application statistics (PS2), full open dataset to 30 June 2026
  2. MHCLG, Live tables on planning application statistics (including table P124A)
  3. MHCLG, District matters data dictionary (definitions of minor dwellings and time bands)
  4. Town and Country Planning (Development Management Procedure) (England) Order 2015, article 34 (time periods for decisions)
  5. MHCLG, Planning practice guidance: Determining a planning application (time periods, extensions of time, non-determination, planning guarantee)
  6. MHCLG, Local authority Green Belt statistics for England: 2025 to 2026

This guide is general information, not legal, tax or financial advice. Every site is different: take advice from a solicitor and an accountant before you sign anything.