How much does planning permission cost? Council fees and the real bill for 1 to 9 homes in 2026
The council's fee is the small part. From 1 April 2026 a full application for a new home in England costs £610 per home. Getting a three-home scheme on a paddock to outline permission costs about £17,400 once you add the drawings, surveys and reports. Here's every fee, what each report costs and when you need it, and what happens if you're refused.
Facts checked against the sources below on 10 November 2026.
Ask what planning permission costs and most answers stop at the council's fee. For new homes that's the smallest line on the bill. The drawings, the planning statement and the surveys a council will want before it validates or approves an application usually cost several times as much. Here's both halves for a landowner with room for one to nine homes in Kent, East Sussex or Surrey, at 2026 prices.
- Council fee per new home, full application, fewer than 10 homes
- £610
- Permission in principle, per 0.1 hectare of site
- £531
- Our worked example: three homes in outline on a half-acre paddock
- £17,400
The council's fee: what each application costs from April 2026
Planning fees in England are set nationally, not by each council, and rise every 1 April in line with inflation. On 1 April 2026 they went up 3.8%, the CPI rate for September 2025. A bigger rise is on the way: draft regulations laid in Parliament would raise the fee to £752 per home, outline to £719 per 0.1 hectare and permission in principle to a flat £825 for applications made from 8 December 2026, if both Houses approve them, and councils are due to get powers to vary fees locally. Until then, these are the fees that matter when you want homes on your land.
| Fee | How it's worked out | |
|---|---|---|
| Full planning permission, 1 to 9 homes | £610 per home | Number of new homes |
| Outline planning permission | £610 per 0.1 ha | Site area, each 0.1 ha or part of it. £659 per 0.1 ha from 0.5 ha |
| Reserved matters (after outline) | £610 per home | The full application fee for the homes covered |
| Permission in principle | £531 per 0.1 ha | Site area, each 0.1 ha or part of it |
| Technical details consent (after PiP) | £610 per home | Treated as a full application |
| Class Q prior approval (barn to home) | £249 or £536 | The higher fee if building works are included |
| Discharge of conditions | £309 | Per request, which can cover several conditions |
| Varying a condition (section 73) | £608 | Non-major schemes |
| Non-material amendment | £309 | Small changes after permission |
The trap is in the two-stage routes. Outline permission settles the principle and usually access, and leaves the design for later. That later application, reserved matters, costs the full £610 per home. The same goes for permission in principle (PiP), where the second stage, technical details consent, is charged as a full application. So outline and PiP are cheaper to start, but dearer in total. Our permission in principle guide explains how the two stages work.
Council fees to reach a buildable permission, by route
Full application against the two-stage routes, from 1 April 2026
- First application
- Second stage (reserved matters or technical details consent)
Show the numbers
| First application | Second stage (reserved matters or technical details consent) | Total | |
|---|---|---|---|
| 1 home: full | £610 | £0 | £610 |
| 1 home: outline, then reserved matters | £610 | £610 | £1,220 |
| 1 home: PiP, then technical details | £531 | £610 | £1,141 |
| 2 homes: full | £1,220 | £0 | £1,220 |
| 2 homes: outline, then reserved matters | £1,220 | £1,220 | £2,440 |
| 2 homes: PiP, then technical details | £1,062 | £1,220 | £2,282 |
| 3 homes: full | £1,830 | £0 | £1,830 |
| 3 homes: outline, then reserved matters | £1,830 | £1,830 | £3,660 |
| 3 homes: PiP, then technical details | £1,593 | £1,830 | £3,423 |
| 5 homes: full | £3,050 | £0 | £3,050 |
| 5 homes: outline, then reserved matters | £2,440 | £3,050 | £5,490 |
| 5 homes: PiP, then technical details | £2,124 | £3,050 | £5,174 |
| 9 homes: full | £5,490 | £0 | £5,490 |
| 9 homes: outline, then reserved matters | £5,272 | £5,490 | £10,762 |
| 9 homes: PiP, then technical details | £4,248 | £5,490 | £9,738 |
Source: MHCLG fee tables from 1 April 2026. Outline and PiP fees depend on site area, not homes: for the chart we've assumed 800 m² (0.08 ha) of site per home, including access. At nine homes that's 0.72 ha, over 0.5 ha, so outline is charged at £659 per 0.1 ha. Council fees only.
Pre-application advice: a Kent example
Pre-application advice isn't set nationally. Each council sets its own charges, and many offer a choice of a letter, a virtual meeting or a site visit. Tonbridge and Malling's charges for 2026/27, including VAT:
| 1 to 4 new homes | 5 to 9 new homes | |
|---|---|---|
| Written advice only | £640 | £957 |
| Virtual meeting and letter | £1,270 | £1,905 |
| Site visit, follow-up meeting and letter | £1,375 | £2,121 |
The council charges again for follow-up questions, and returns enquiries that ask about several different options at once. Other councils in Kent, Sussex and Surrey charge different amounts, so check the council's own page. Pre-app advice isn't binding, but in our experience a positive response is worth having on file, and a negative one can save the cost of a full set of reports.
Everything else: the reports a small housing scheme needs
Councils publish a local validation list setting out what has to come with an application. For one to nine homes on a field or paddock, these are the usual items. The ranges are typical fees in our experience in the South East in 2026, not official figures, and quotes vary with the site and the firm.
Planning consultant: typically £2,500 to £8,000
Writes the planning statement that argues the case against local and national policy, manages the application and deals with the council. Optional in law, but on a contested site it often decides the outcome.
Architect's drawings: typically £2,000 to £5,000 for outline, £5,000 to £15,000 for full
Location plan, site layout and, for a full application or reserved matters, floor plans and elevations for every home. Usually needs a topographical survey first, typically £800 to £2,000.
Ecology: typically £800 to £1,500 for a preliminary appraisal
Most green sites need a preliminary ecological appraisal. If it finds signs of bats, great crested newts or reptiles, further surveys follow, often £1,000 to £5,000 more, and some can only be done at certain times of year, which can cost you months.
Biodiversity net gain: typically £1,000 to £3,000, sites over 0.2 hectares
From 6 August 2026, sites of 0.2 hectares or less are exempt from BNG unless they affect a priority habitat such as a native hedgerow. Bigger sites need a metric calculation, and possibly off-site units if the site can't deliver the 10% gain itself. Our BNG exemptions guide explains the threshold.
Access and transport: typically £1,000 to £3,000
A transport or access statement showing a safe access with adequate visibility. The county council (or Medway or Brighton & Hove in their areas) comments as highway authority. A speed survey to justify shorter visibility splays adds to the cost.
Trees: typically £600 to £2,000
An arboricultural survey and impact assessment wherever there are trees on or next to the site.
Drainage and flood risk: typically £800 to £3,000
A drainage strategy for surface water, and a flood risk assessment if any part of the site is in flood zone 2 or 3, or the site is in a critical drainage area. Percolation tests may be needed to prove soakaways work.
Heritage, where relevant: typically £800 to £2,500
A heritage statement if the site is in or next to a conservation area, or near a listed building.
Worked example: three homes in outline on a half-acre paddock
Take a 0.5 acre paddock on the edge of a Kent village: 2,023 m², or 0.2023 hectares, with a field gate onto a lane, a hedge along the road and no heritage constraints. The owner applies for outline permission for three homes with access. Note that half an acre is just over the 0.2 hectare BNG threshold, so BNG applies unless the red line can be drawn tighter. The professional fees are taken from the lower half of our typical ranges, so a well-constrained site could cost more.
| Pre-application advice (Tonbridge and Malling, virtual meeting and letter) | £1,270 |
|---|---|
| Outline application fee (three parts of 0.1 ha at £610) | £1,830 |
| Planning consultant (typical) | £4,000 |
| Architect, location plan and indicative layout (typical) | £3,000 |
| Topographical survey (typical) | £1,000 |
| Preliminary ecological appraisal (typical) | £1,200 |
| BNG metric, site over 0.2 ha (typical) | £1,500 |
| Access and transport statement (typical) | £1,500 |
| Arboricultural survey (typical) | £900 |
| Drainage strategy (typical) | £1,200 |
| Cost to reach a decision on outline permission | about £17,400 |
Illustrative. Council and pre-app fees are the published 2026/27 figures; everything else is from the lower half of our typical ranges, not a quote. Not included: further protected species surveys, off-site BNG units, legal costs of a section 106 agreement, then the reserved matters stage: £1,830 in council fees plus detailed drawings, often another £5,000 to £15,000.
Two things stand out. The council takes about £3,100 of the total, under a fifth. And most of the rest is spent before anyone knows whether permission will be granted, which is why a refusal hurts.
If you're refused
Resubmitting pays the full fee again
The 'free go', a free repeat application by the same applicant within 12 months, was abolished on 6 December 2023. A revised application in 2026 pays the full fee, and usually needs updated reports too.
Appealing is free, but not cheap
There's no fee to appeal to the Planning Inspectorate. For a refused application for new homes you have six months from the decision. The cost is a planning consultant's appeal statement, often £2,000 to £5,000 in our experience for a small scheme decided in writing, and more if it goes to a hearing.
Since April 2026, most appeals allow no new evidence
For applications made on or after 1 April 2026, every appeal against a refusal starts under the expedited 'part 1' written procedure: the inspector decides on the application the council saw, and new evidence is only accepted in narrow cases such as a change in planning policy or a court judgment. The Inspectorate can move a case to a hearing or inquiry, but a missing survey can't be fixed at appeal.
Costs are only awarded for unreasonable behaviour
Each side normally pays its own appeal costs. If the council refused without good reason, you can apply for an award of costs, but only for the appeal, never for the original application.
Who pays: you, a developer, or a promoter
If you apply yourself, you carry every cost above and the risk of losing it. If you sell to a developer without planning, they pay for planning but price the risk into what they offer. Under an option or promotion agreement, the developer or promoter pays for the application, the reports and any appeal, and you share in the value once permission is granted.
On PLOT's routes the landowner pays nothing up front. We fund the planning, including the applications, the surveys and reports, and any appeal, whether you then take a fixed price from a developer or a share of self-build plot sales.
To see what your land could be worth with permission, our land value calculator takes the area in acres, square metres, or a width and length, and shows the figures line by line.
Read next
- Selling land to a developer: how it works and what you're paidThe four ways to sell land to a developer, how a developer works out what to pay, what they check before buying, how long it takes, and the traps to avoid.
- Option agreements: the terms that matter to landownersHow an option agreement on land works: the option fee, how the price is set, the discount, minimum price, longstop date, tax, and promotion agreements.
- A third of small housing applications in Kent, East Sussex and Surrey are now decided within eight weeksOnly 34% of applications for one to nine homes in Kent, East Sussex and Surrey were decided within eight weeks in the year to June 2026, against 77% in 2010.
Common questions
How much does planning permission cost for one house?
The council fee for a full application for one new house in England is £610 from 1 April 2026, and outline permission for a site under 0.1 hectares is also £610. The fee is the small part. In our experience drawings, a planning statement, surveys and reports usually take the total for a single plot to somewhere between £5,000 and £15,000, depending on how many reports the site needs.
How much is a planning application for two or three houses?
A full application costs £610 per home, so £1,220 for two and £1,830 for three. Outline is charged on site area instead: £610 for each 0.1 hectare or part of it, on sites under 0.5 hectares. A 0.5 acre site (0.2023 hectares) pays £1,830 whatever the number of homes, then £610 per home again at reserved matters.
Do you get a free resubmission after planning is refused?
No, not in England. The 'free go', which let the same applicant resubmit for similar development on the same site within 12 months without paying, was abolished by the 2023 fee regulations from 6 December 2023. Every resubmission now pays the full fee.
How much does a planning appeal cost?
There's no fee to appeal to the Planning Inspectorate. The cost is the professional time to prepare it. Each side normally pays its own costs, and costs are only awarded against a party that behaves unreasonably. For applications made on or after 1 April 2026, most written appeals against a refusal follow an expedited procedure with no new evidence, so the case rests on what went in with the application.
Do I get my planning fee back if the council is late?
Sometimes. Under the Planning Guarantee, the fee for a non-major application (fewer than ten homes on a site under a hectare) must be refunded if there's no decision within 16 weeks, unless you've agreed a longer period in writing or have already appealed for non-determination. Councils often ask applicants to agree an extension, and agreeing one gives up the refund.
Who pays for planning when you sell land to a developer?
It depends on the deal. With a straight sale the buyer usually pays after completion. Under an option agreement or a promotion agreement the developer or promoter normally pays for the application, the reports and any appeal, and recovers that from the eventual sale. On both of PLOT's routes the landowner pays nothing up front.
Sources
- MHCLG: Planning fees, annual indexation from 1 April 2026 (fee tables for England)
- The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012 (SI 2012/2920), as amended
- The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment) Regulations 2023 (SI 2023/1197): revocation of the repeat application exemptions
- MHCLG Planning Practice Guidance: Fees for planning applications (reserved matters, refunds and the Planning Guarantee)
- MHCLG Planning Practice Guidance: Permission in principle (technical details consent fees)
- Tonbridge and Malling Borough Council: Pre-application planning advice
- Tonbridge and Malling Borough Council: Pre-application charging schedule 2026/27
- Defra: Biodiversity net gain, exempt developments
- MHCLG: Community Infrastructure Levy guidance (liability and self-build exemption)
- GOV.UK: Appeal against a planning decision (no fee)
- Planning Inspectorate: Planning appeals procedural guide, for applications dated on or after 1 April 2026
- MHCLG: Fees for planning applications, government response (16 July 2026)
- Draft Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026 (proposed fees from 8 December 2026)
This guide is general information, not legal, tax or financial advice. Every site is different: take advice from a solicitor and an accountant before you sign anything.